Lititz WTP Filter Improvements
The Lititz Filter Improvement project included a complete overhaul and rehabilitation of each of three filters in the Lititz Water Treatment Facility. This included removal of the existing media, sandblasting and painting of the existing metal tank filters and reinstallation of new media. Each filter had to be completed individually in order to keep water service operational to the town. It took about 120 days to complete each filter after testing and confirmation.
Location
Lititz, PA
Contract Amount
954,711
Engineer
Entech Engineering, Inc.
Owner
Borough of Lititz
Schedule a Consultation
Contact Us
Start Your Project with M2 Construction