Lititz WTP Filter Improvements

The Lititz Filter Improvement project included a complete overhaul and rehabilitation of each of three filters in the Lititz Water Treatment Facility. This included removal of the existing media, sandblasting and painting of the existing metal tank filters and reinstallation of new media. Each filter had to be completed individually in order to keep water service operational to the town. It took about 120 days to complete each filter after testing and confirmation.

Location

Lititz, PA

Contract Amount

954,711

Engineer

Entech Engineering, Inc.

Owner

Borough of Lititz