Carmany Road WTP Nitrate Resin Replacement

The project included a complete overhaul and rehabilitation of each of three nitrate removal filters in the Facitlity in Mount Joy Borough. This included removal of the existing media, sandblasting and painting of the existing metal tank fitlers (both inside and outside) and reinstallation and testing of new media. Each filter had to be completed individually in order to keep water service operational to the town. It took about 100 days to complete each filter.

Location

Mount Joy, PA

Contract Amount

594,611

Engineer

Arro Consulting

Owner

Mount Joy Borough Authority