Bioenergy Devco, LLC Maryland Food Center
M2 Construction installed the cast in place concrete for BioDevco’s Food Waste Plant in Jessup, MD. The work included all the foundations, footers, piers and walls for the metal building installation as well as the 4000 Sq foot slab. M2 constructed a process tank with 40′ walls, some as thick at 32″ for use with the plant. This was a complicated project that was completed over the course of 14 months and included over 4500 cubic yards of concrete.